| HAVEN CONSTRUCTION COMMITMENT EVALUATION | ||||||
| Dan Nielsen | ||||||
| Month | Hours Per Month | Cumulative Hours | Dollars Per Month | Cumulative Dollars | Project Activity At End Of Month | |
| 1 | 54 | 54 | 746 | 746 | Making Stem | |
| 2 | 41 | 95 | 713 | 1459 | Transom Beveling | |
| 3 | 36 | 131 | 282 | 1741 | Initial Mold Setup | |
| 4 | 23 | 154 | 0 | 1741 | Beveling Molds | |
| 5 | 41 | 195 | 604 | 2345 | Bending Frames | |
| 6 | 57 | 252 | 630 | 2975 | Attaching Floor Timbers | |
| 7 | 33 | 285 | 430 | 3405 | Shaping Wood Keel | |
| 8 | 33 | 318 | 617 | 4022 | Priming (Red Lead) Frames | |
| 9 | 26 | 344 | 0 | 4022 | Mounting Garboards | |
| 10 | 51 | 395 | 0 | 4022 | Mounting Plank #4 | |
| 11 | 74 | 469 | 263 | 4285 | Mounting Plank #9 | |
| 12 | 53 | 522 | 396 | 4681 | Mounting Sheer Strakes | |
| 13 | 86 | 608 | 277 | 4958 | Painting Hull | |
| 14 | 60 | 668 | 284 | 5242 | Mounting Sheer Clamps | |
| 15 | 43 | 711 | 380 | 5622 | Mounting Deck Beams | |
| 16 | 32 | 743 | 90 | 5712 | Mounting Floor Beams | |
| 17 | 51 | 794 | 288 | 6000 | Decking | |
| 18 | 14 | 808 | 141 | 6141 | Making/Mounting Chain Plates | |
| 19 | 59 | 867 | 298 | 6439 | Making/Mounting Coamings | |
| 20 | 39 | 906 | 227 | 6666 | Mounting Toe Rails | |
| 21 | 24 | 930 | 64 | 6730 | Making Floor | |
| 22 | 61 | 991 | 1399 | 8129 | Making Seats | |
| 23 | 45 | 1036 | 1869 | 9998 | Completing Interior Trim | |
| 24 | 68 | 1104 | 966 | 10964 | Making Lead Keel | |
| 25 | 48 | 1152 | 292 | 11256 | Making Rudder and Centerboard | |
| 26 | 50 | 1202 | 18 | 11274 | Making Spars | |
| 27 | 70 | 1272 | 5906 | 17180 | Making Oars and Rigging | |
| 1272 | 17180 | TOTALS | ||||